Joint replacement in an operational planning phase
Publication
Publication
European Journal of Operational Research , Volume 91 - Issue 1 p. 74- 88
We consider the problem of combining replacements of multiple components in an operational planning phase. Within an infinite or finite time horizon, decisions concerning replacement of components are made at discrete time epochs. The optimal solution of this problem is limited to only a small number of components. We present a heuristic rolling horizon approach that decomposes the problem; at each decision epoch an initial plan is made that